Miscellaneous construction projects and upgrades - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 10 |
DATE | January 2013 - December 2013 |
Amine upgrade; Boilerhouse and DCS upgrade - Electrical and Instrumentation installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 25 |
DATE | March 2013 - December 2013 |
Mine expansion project.
CUSTOMER | Gisborne Industrial Contractors |
---|---|
PEAK WORKFORCE | 15 |
DATE | March 2013 - August 2013 |
Recovery Boiler Re & Re - Electrical and instrumentation installations.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | May 2013 - June 2013 |
Installation of network and fibre optic control system; commissioning of plant and process equipment.
CUSTOMER | Thompson Creek Metals |
---|---|
PEAK WORKFORCE | 8 |
DATE | July 2013 - December 2014 |
Commissioning assistance of plant process equipment and start up.
CUSTOMER | Thomspon Creek Metals |
---|---|
PEAK WORKFORCE | 30 |
DATE | July 2013 - December 2014 |
Genset Install.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 8 |
DATE | August 2013 - December 2013 |
Electrical installations for Depot upgrade.
CUSTOMER | Ridgeview Construction |
---|---|
PEAK WORKFORCE | 6 |
DATE | September 2013 - March 2014 |
Electrical and instrumentation - Bleach Plant and Brown Stock DCS upgrade.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 24 |
DATE | April 2014 - September 2014 |
Electrical installations for medium voltage MCC 5 Kv replacement.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 32 |
DATE | April 2014 - September 2014 |
Electrical installations for medium voltage MCC 5 Kv replacement.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 32 |
DATE | April 2014 - September 2014 |
Lignin Recovery Plant - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 8 |
DATE | April 2014 - December 2014 |
Electrical and instrumentation installations for Cooling Water upgrade.
CUSTOMER | The Gisborne Group |
---|---|
PEAK WORKFORCE | 5 |
DATE | July 2014 - July 2015 |
Electrical and instrumentation installations for load bank.
CUSTOMER | CIMS Limited Partnership |
---|---|
PEAK WORKFORCE | 10 |
DATE | August 2014 - November 2014 |
Instrumentation maintenance support.
CUSTOMER | MacKenzie Pulp Mill Corp. |
---|---|
PEAK WORKFORCE | 4 |
DATE | September 2014 - May 2015 |
Electrical and instrumentation installations for Phase I and II of Genset installation.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 10 |
DATE | September 2014 - August 2015 |
Electrical and instrumentation installations for steam turbine generator upgrade.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | November 2014 - April 2015 |
Electrical and instrumentation installations for fire alarm system.
CUSTOMER | Tyco - Simplex Grinnell |
---|---|
PEAK WORKFORCE | 10 |
DATE | November 2014 - April 2015 |
Underground electrical and instrumentation expansion.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | January 2015 - present |
Electrical installations for Powerhouse upgrades and gensets.
CUSTOMER | International Quest Engineering Ltd. |
---|---|
PEAK WORKFORCE | 7 |
DATE | January 2015 - present |