Hinton Pulp Mill - Various Upgrades - Hinton, AB

Miscellaneous construction projects and upgrades - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 10
DATE January 2013 - December 2013

Husky Energy - Boilerhouse House Electrical Upgrade - Prince George, BC

Amine upgrade; Boilerhouse and DCS upgrade - Electrical and Instrumentation installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 25
DATE March 2013 - December 2013

LIM - Labrador Iron Mine - Nfld & Labrador

Mine expansion project.

CUSTOMER Gisborne Industrial Contractors
PEAK WORKFORCE 15
DATE March 2013 - August 2013

Canfor - Northwood Pulp - Prince George, BC

Recovery Boiler Re & Re - Electrical and instrumentation installations.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE May 2013 - June 2013

Mt. Milligan - Thompson Creek Metals - Mt. Milligan, BC

Installation of network and fibre optic control system; commissioning of plant and process equipment.

CUSTOMER Thompson Creek Metals
PEAK WORKFORCE 8
DATE July 2013 - December 2014

Mt. Milligan - Thompson Creek Metals - Mt. Milligan, BC

Commissioning assistance of plant process equipment and start up.

CUSTOMER Thomspon Creek Metals
PEAK WORKFORCE 30
DATE July 2013 - December 2014

DeBeers - Snap Lake Diamond Mine - Snap Lake, Northwest Territories

Genset Install.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 8
DATE August 2013 - December 2013

Bandstra Trucking - Depot Upgrade - Prince George, BC

Electrical installations for Depot upgrade.

CUSTOMER Ridgeview Construction
PEAK WORKFORCE 6
DATE September 2013 - March 2014

Hinton Pulp Mill - DCS Upgrade - Hinton, AB

Electrical and instrumentation - Bleach Plant and Brown Stock DCS upgrade.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 24
DATE April 2014 - September 2014

Hinton Pulp Mill - MCC 5 Kv Replacement - Hinton, AB

Electrical installations for medium voltage MCC 5 Kv replacement.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 32
DATE April 2014 - September 2014

Hinton Pulp Mill - MCC 5 Kv Replacement - Hinton, AB

Electrical installations for medium voltage MCC 5 Kv replacement.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 32
DATE April 2014 - September 2014

Hinton Pulp Mill - Lignin Recovery Plant Phase I - Hinton, AB

Lignin Recovery Plant - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 8
DATE April 2014 - December 2014

BC Hydro - Bridge River Power Project - Bridge River, BC

Electrical and instrumentation installations for Cooling Water upgrade.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 5
DATE July 2014 - July 2015

Spectra Energy - Load Bank - Port Coquitlam, BC

Electrical and instrumentation installations for load bank.

CUSTOMER CIMS Limited Partnership
PEAK WORKFORCE 10
DATE August 2014 - November 2014

MacKenzie Pulp Mill - Maintenance - MacKenzie, BC

Instrumentation maintenance support.

CUSTOMER MacKenzie Pulp Mill Corp.
PEAK WORKFORCE 4
DATE September 2014 - May 2015

Genalta Power - Genset Installation Phase I & II - Peace River, BC

Electrical and instrumentation installations for Phase I and II of Genset installation.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 10
DATE September 2014 - August 2015

Canfor - Intercon Steam Turbine Generator - Prince George, BC

Electrical and instrumentation installations for steam turbine generator upgrade.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE November 2014 - April 2015

Red Chris Mine - Fire Alarm - Dease Lake, BC

Electrical and instrumentation installations for fire alarm system.

CUSTOMER Tyco - Simplex Grinnell
PEAK WORKFORCE 10
DATE November 2014 - April 2015

De Beers Canada - Underground Expansion - Snap Lake, Northwest Territories

Underground electrical and instrumentation expansion.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE January 2015 - present

De Beers Canada - Powerhouse Upgrades - Snap Lake, Northwest Territories

Electrical installations for Powerhouse upgrades and gensets.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE January 2015 - present