CWP LRU 014 - 015 - Electrical Installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 30 |
DATE | April 2011 - December 2011 |
Installation of mill-wide fire alarm system.
CUSTOMER | Simplex Grinnell |
---|---|
PEAK WORKFORCE | 8 |
DATE | April 2011 - December 2011 |
Electrical and instrumentation installations for heavy media coal processing facility.
CUSTOMER | Robers & Schaefer Company |
---|---|
PEAK WORKFORCE | 28 |
DATE | April 2011 - April 2012 |
Steam Plant DCS upgrade.
CUSTOMER | MacKenzie Pulp Corp. |
---|---|
PEAK WORKFORCE | 20 |
DATE | May 2011 - October 2011 |
Refuse recovery, raw coal system and lighting supply; wash plant extension.
CUSTOMER | Taggart Global |
---|---|
PEAK WORKFORCE | 25 |
DATE | June 2011 - November 2012 |
Electrical installations for Mill Security systems at all three Prince George mills.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 15 |
DATE | July 2011 - August 2011 |
Electrical and instrumentation installations for PM2 Upgrade.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 30 |
DATE | July 2011 - December 2011 |
Electrical and instrumentation installations for new Pressure Diffuser.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 10 |
DATE | July 2011 - March 2012 |
Site-wide electrical and instrumentation installations, new truck shop and administration facility.
CUSTOMER | Walter Energy, Western Coal Corp. |
---|---|
PEAK WORKFORCE | 12 |
DATE | July 2011 - April 2012 |
Electrical and instrumentation installations for evaporator upgrade.
CUSTOMER | MacKenzie Pulp Mill Corp. |
---|---|
PEAK WORKFORCE | 12 |
DATE | August 2011 - December 2011 |
Electrical and instrumentation installations for various construction and upgrade projects (truck scale and water chiller).
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 6 |
DATE | January 2012 - December 2012 |
Electrical and instrumentation installations for boiler feedwater.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | March 2012 - September 2012 |
Demolition of existing Chlorate III Rectifier - electrical.
CUSTOMER | Chemtrade Logisitics |
---|---|
PEAK WORKFORCE | 20 |
DATE | April 2012 - November 2012 |
Wastewater Contract 3A - Electrical and Instrumentation Installations.
CUSTOMER | Husky Energy |
---|---|
PEAK WORKFORCE | 30 |
DATE | April 2012 - December 2012 |
Recovery boiler Re & Re, tertiary fan and precipitator ID fan - electrical and instrumentation installations.
CUSTOMER | Canfor Pulp Limited Partnership |
---|---|
PEAK WORKFORCE | 25 |
DATE | May 2012 - September 2012 |
Electrical Installations.
CUSTOMER | Dowland Industrial Works Ltd. |
---|---|
PEAK WORKFORCE | 6 |
DATE | June 2012 - April 2013 |
Powerhouses, substations and intake buildings - electrical and instrumentation installations.
CUSTOMER | Eaton Corporation |
---|---|
PEAK WORKFORCE | 15 |
DATE | June 2012 - June 2014 |
Installation of mill-wide fire alarm system.
CUSTOMER | Gisborne Industrial Construction Ltd. |
---|---|
PEAK WORKFORCE | 15 |
DATE | June 2012 - November 2013 |
Mine process expansion including site-wide fibre optic infrastructure; electrical and instrumentation installation of new Moly Plant and Brownfield areas.
CUSTOMER | Gibraltar Mine Ltd. |
---|---|
PEAK WORKFORCE | 80 |
DATE | August 2012 - July 2013 |
PM2 DCS Migration - Electrical and instrumentation installations.
CUSTOMER | West Fraser Mills |
---|---|
PEAK WORKFORCE | 4 |
DATE | January 2013 - April 2014 |