Husky Energy - Load Rack Upgrade - Prince George Refinery - Prince George, BC

CWP LRU 014 - 015 - Electrical Installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 30
DATE April 2011 - December 2011

Endako / Thompson Creek Mine - Fire Alarm - Endako, BC

Installation of mill-wide fire alarm system.

CUSTOMER Simplex Grinnell
PEAK WORKFORCE 8
DATE April 2011 - December 2011

Elkview Mine - Heavy Media Coal Processing - Fernie, BC

Electrical and instrumentation installations for heavy media coal processing facility.

CUSTOMER Robers & Schaefer Company
PEAK WORKFORCE 28
DATE April 2011 - April 2012

MacKenzie Pulp Corp. - DCS Upgrade - MacKenzie, BC

Steam Plant DCS upgrade.

CUSTOMER MacKenzie Pulp Corp.
PEAK WORKFORCE 20
DATE May 2011 - October 2011

Willow Creek Minesite - Refuse, Raw Coal, Lighting - Chetwynd, BC

Refuse recovery, raw coal system and lighting supply; wash plant extension.

CUSTOMER Taggart Global
PEAK WORKFORCE 25
DATE June 2011 - November 2012

Canfor - Northwood, PG Pulp, Intercon Security System - Prince George, BC

Electrical installations for Mill Security systems at all three Prince George mills.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 15
DATE July 2011 - August 2011

Hinton Pulp Mill - PM2 Upgrade - Hinton, AB

Electrical and instrumentation installations for PM2 Upgrade.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 30
DATE July 2011 - December 2011

Hinton Pulp Mill - New Pressure Diffuser - Hinton, AB

Electrical and instrumentation installations for new Pressure Diffuser.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 10
DATE July 2011 - March 2012

Brule Mine - New Truck Shop / Admin Building - Chetwynd, BC

Site-wide electrical and instrumentation installations, new truck shop and administration facility.

CUSTOMER Walter Energy, Western Coal Corp.
PEAK WORKFORCE 12
DATE July 2011 - April 2012

MacKenzie Pulp Corp. - Evaporator Upgrade - MacKenzie, BC

Electrical and instrumentation installations for evaporator upgrade.

CUSTOMER MacKenzie Pulp Mill Corp.
PEAK WORKFORCE 12
DATE August 2011 - December 2011

Hinton Pulp Mill - Truck Scale & Water Chiller - Hinton, AB

Electrical and instrumentation installations for various construction and upgrade projects (truck scale and water chiller).

CUSTOMER West Fraser Mills
PEAK WORKFORCE 6
DATE January 2012 - December 2012

Canfor - PG Pulp Boiler Feedwater - Prince George, BC

Electrical and instrumentation installations for boiler feedwater.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE March 2012 - September 2012

Chemtrade Logistics - Chlorate III Rectifier - Prince George, BC

Demolition of existing Chlorate III Rectifier - electrical.

CUSTOMER Chemtrade Logisitics
PEAK WORKFORCE 20
DATE April 2012 - November 2012

Husky Energy - Wastewater Treatment - Prince George, BC

Wastewater Contract 3A - Electrical and Instrumentation Installations.

CUSTOMER Husky Energy
PEAK WORKFORCE 30
DATE April 2012 - December 2012

Canfor - PG Pulp Recovery Boiler - Prince George, BC

Recovery boiler Re & Re, tertiary fan and precipitator ID fan - electrical and instrumentation installations.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 25
DATE May 2012 - September 2012

Dasque Cluster Hydro-Electrical Project - Terrace, BC

Electrical Installations.

CUSTOMER Dowland Industrial Works Ltd.
PEAK WORKFORCE 6
DATE June 2012 - April 2013

Middle & Dasque Creek Powerhouse - Terrace, BC

Powerhouses, substations and intake buildings - electrical and instrumentation installations.

CUSTOMER Eaton Corporation
PEAK WORKFORCE 15
DATE June 2012 - June 2014

Mt. Milligan - Fire Alarm System - Mt. Milligan, BC

Installation of mill-wide fire alarm system.

CUSTOMER Gisborne Industrial Construction Ltd.
PEAK WORKFORCE 15
DATE June 2012 - November 2013

Gibraltar Mine Ltd. - GDP3 Project - McLeese Lake, BC

Mine process expansion including site-wide fibre optic infrastructure; electrical and instrumentation installation of new Moly Plant and Brownfield areas.

CUSTOMER Gibraltar Mine Ltd.
PEAK WORKFORCE 80
DATE August 2012 - July 2013

Hinton Pulp Mill - PM2 DCS Migration - Hinton, AB

PM2 DCS Migration - Electrical and instrumentation installations.

CUSTOMER West Fraser Mills
PEAK WORKFORCE 4
DATE January 2013 - April 2014