Ekati Diamond Mine - Processing Plant - Northwest Territories

Upgrades to process power and controls system.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 4
DATE April 2004 - November 2005

Canfor - PG Pulp Co-Gen Project - Prince George, BC

Construction of a new 60 megawatt Co-generation facility including substation, hog fuel unloading and handling conveyors, power distribution, concentrator, cooling tower and precipitator, converting two existing boilers.

CUSTOMER Canfor Pulp Limited Partnership
PEAK WORKFORCE 50
DATE June 2004 - April 2006

Wolverine Coal - New Coal Mine - Tumbler Ridge, BC

Construction of new coal mine including substation, crusher, preparation plant, materials handling conveyors, rail load-out and refuse bin.

CUSTOMER Western Canadian Coal Corp., Robertson P & E, Inc.
PEAK WORKFORCE 25
DATE July 2005 - November 2007

Husky Energy - Clean Fuels Upgrade - Prince George, BC

Power and controls and DCS upgrade for Clean Fuels upgrade project, general plant upgrades.

CUSTOMER Husky Energy
PEAK WORKFORCE 10
DATE July 2005 - January 2006

Duke Energy - Compressor Stations and Processing Plants - Various locations, BC

Power and controls upgrades.

CUSTOMER Duke Energy
PEAK WORKFORCE 7
DATE October 2005 - Februrary 2006

Spectra Energy - Compressor Stations and Processing Plants - Various locations, BC

Power and Controls upgrade.

CUSTOMER Spectra Energy
PEAK WORKFORCE 12
DATE October 2005 - February 2014

Ekati Diamond Mine - Small Diamond Recovery - Northwest Territories

Installation of small diamond recovery plant process power and control systems.

CUSTOMER BHP Billiton - Internation Quest Engineering Ltd.
PEAK WORKFORCE 8
DATE February 2006 - December 2006

West Fraser Mills - Hinton Pulp Mill - Hinton, AB

Head box replacement; electrical and instrumentation for high density system; bleach plant DCS migration; medium voltage switchgear replacement.

CUSTOMER West Fraser Mills Ltd.
PEAK WORKFORCE 30
DATE January 2007 - May 2007

Wolverine Coal Mine - Services Complex - Tumbler Ridge, BC

Construction of new coal mine services complex and installation of 2 MVA back-up generator system.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 15
DATE May 2007 - July 2008

Ekati Diamond Mine - Glycol Heat Recovery - Northwest Territories

Process power and controls system.

CUSTOMER BHP Billiton - Internation Quest Engineering Ltd.
PEAK WORKFORCE 7
DATE June 2007 - April 2008

Diavik Diamond Mine - Audit Plant Modifications - Northwest Territories

Power and control modifications to existing audit plant systems.

CUSTOMER International Quest Engineering Ltd.
PEAK WORKFORCE 2
DATE December 2007

Baymag Plant II - Calcining Facility Phase 2A - Canmore, AB

Installation of electrical and instrumentation for new facility.

CUSTOMER Baymag Inc.
PEAK WORKFORCE 20
DATE September 2008 - May 2009

BC Hydro - Williston Substation - Prince George, BC

Modification to 500 Kv switches and installation of new 500 Kv breakers.

CUSTOMER Mutual Construction (2000) Ltd.
PEAK WORKFORCE 5
DATE September 2008 - November 2008

Dokie Wind Farm Project - Chetwynd, BC

Installation of substation and wind farm towers and bases.

CUSTOMER Earth First
PEAK WORKFORCE 10
DATE October 2008 - December 2010

Wolverine Mine - New Facilities - Yukon Territories

Installation of new Crusher Building, new Mill Building, new Truck Shop, plant-wide fire alarm and power generation; complete instrumentation installations including calibration, commissioning, start-up assistance, maintenance and consulting services.

CUSTOMER Yukon Zinc Corporation
PEAK WORKFORCE 95
DATE January 2009 - December 2011

Husky Energy - Plant Electrical Upgrade - Prince George, BC

Plant electrical upgrade including replacement of medium voltage transformers, replacement of MCCs, and replacement of existing power and motor control conduit distribution system.

CUSTOMER Husky Energy
PEAK WORKFORCE 35
DATE June 2009 - December 2010

BC Hydro - Generator Modifications - Aberfeldie Dam Site, BC

Provide assistance to BC Hydro personnel for modifications to generator high voltage terminations.

CUSTOMER Kamtech Services
PEAK WORKFORCE 4
DATE November 2010 - June 2011

Copper Mountain - Freshwater Reclaim - Princeton, BC

Installation of Freshwater Reclaim system, commissioning, and start-up.

CUSTOMER Similco Mines Ltd.
PEAK WORKFORCE 12
DATE March 2011

Copper Mountain - Fire Alarm - Princeton, BC

Installation of mill-wide fire alarm system.

CUSTOMER Simplex Grinnell
PEAK WORKFORCE 12
DATE March 2011 - June 2011

Copper Mountain - QA / QC - Princeton, BC

Provide QA/QC personnel to gather data and develop reports.

CUSTOMER The Gisborne Group
PEAK WORKFORCE 5
DATE March 2011 - June 2011

24 HOUR EMERGENCY SERVICE
250.563.4100 • CLASS A LICENSED & BONDED